New Church Building Progress

Keep watching this page to see our new church construction! (Click on the photos to see enlargement)

January 12, 2017 – The walls are going up.

January 2, 2018 – The floor slab is poured and leveled.

December 14, 2017 – The footings for the events shelter are being poured.

December 12, 2017 – The wire mesh for the concrete slab is going in. Almost ready to pour the slab.

December 1, 2017 – The base gravel and post forms for the outdoor events shelter are in place.

November 21, 2017 – In steady rain, workers are filling the inside of the foundation with fine gravel and compacting as they go.

November 15, 2017 – The underground pipes for the roof drains are going in. The septic system and parking lot are under construction also.

November 1, 2017 – The stem walls have been poured, insulation and sewer pipes are going in.

October 16, 2017 – The footings have been poured and the stem wall forms are being installed.

September 15, 2017 – Rebar is being wired into the concrete forms.

August 29, 2017 – Concrete forms for the footings are in place.

July 28, 2017 – Construction stakes have been placed and sod has been removed for the rain gardens for the new parking lot. You can see the contractor’s trailer set up by the building site.