New Church Progress

Keep watching this page to see our new church construction! (Click on the photos to see enlargement)

November 15, 2017 – The underground pipes for the roof drains are going in. The septic system and parking lot are under construction also.

November 1, 2017 – The stem walls have been poured, insulation and sewer pipes are going in.

October 16, 2017 – The footings have been poured and the stem wall forms are being installed.

September 15, 2017 – Rebar is being wired into the concrete forms.

August 29, 2017 – Concrete forms for the footings are in place.

July 28, 2017 – Construction stakes have been placed and sod has been removed for the rain gardens for the new parking lot. You can see the contractor’s trailer set up by the building site.